How much sand and cement do I need for screed?

Cement and sharp sand per square metre for a 4:1 screed at 40 to 75 mm, bags for 5, 10 and 20 m², and the pre-mixed alternative.

A traditional floor screed is sharp sand and cement, usually four parts sand to one part cement, mixed fairly dry and laid to a level. The amount comes from the area and the depth.

Per square metre

One square metre at 50 mm is 0.05 m³ of screed. The dry materials take up more room before water is added, so the calculator uses 1.33 times the wet volume. At 4:1 a fifth of that is cement, at 1440 kg/m³, and the rest is sharp sand at 1600 kg/m³.

4:1 sand and cement per square metre, no waste
DepthCementSharp sandPre-mixed at 2 kg/m²/mm
40 mm15.3 kg68 kg80 kg
50 mm19.2 kg85 kg100 kg
65 mm24.9 kg111 kg130 kg
75 mm28.7 kg128 kg150 kg

Bags for a room

A 15 m² floor at 50 mm with 10% waste is 0.825 m³: 316 kg of cement, which is 12.6 bags of 25 kg, so 13, and about 1404 kg of sharp sand, two 800 kg bulk bags.

For 5 m² it is 5 bags of cement and one bulk bag of sand. For 10 m² it is 9 bags and two bulk bags. For 20 m² it is 17 bags and three bulk bags. In Australia, with 20 kg cement and 1 tonne sand bags, the same floors take 6, 11 and 22 bags of cement.

Pre-mixed screed

Bagged screed costs more per square metre but saves mixing. The Easy Mix Traditional Floor Screed data sheet says a 20 kg bag covers about 1 m² at 10 mm, which is 2 kg per square metre per millimetre. At 50 mm that is 100 kg a square metre, five bags, so it suits small areas and patches.

Depth

Measure the depth in several places and use the average; floors are rarely flat before screeding. Bonded, unbonded and floating screeds each have a minimum thickness, and underfloor heating adds its own. Follow the specification for your floor; this page only turns a depth into materials.

Figures are estimates for a shopping list. Check the pack or datasheet before you buy.

Work it out with your measurements

More guides